WEEK 1:
Factory: Module floors are assembled.
Site: A single family house site, previously cleared.
WEEK 2:
Factory: All modules framed,
wiring/piping being installed
Site: Site Utilities installed.
WEEK 5:
Factory: Drywall.
Site: Foundation stem walls poured.
WEEK 8:
Factory: Modules painted,
equipment installed, ready for shipping.
Site: Foundation ready for installation.
WEEK 9 - Installation Day 1:
Crane set up, first module arrives on site.
WEEK 9 - Installation Day 1:
Module #5 being installed
(Floor 3 Two bedroom unit).
WEEK 9 - Installation Day 3:
Module #15 being installed
(Floor 3 Studio).
MONTH 5:
Siding being installed.
MONTH 6:
Completed project.
<
>